Castle Towers Shopping Centre - Stage 2

Project Features

  • Large scale multistage development project
  • Occupied and operational buildings
  • 6 x new and 3 x relocated water cooled chillers
  • 9 x super quiet high-volume BAC cooling towers
  • 27 x primary and secondary chilled and condenser water pumps
  • 3 x natural gas fired boilers
Sector
Year Completed
2018

Project Details

Located in Castle Hill, Sydney, the Castle Towers Shopping Centre is currently undergoing a major transformation that when complete will see it become Australia’s second largest shopping precinct. With an estimated 18 million visitors per year, work is being delivered in stages to minimise the disruption to tenants and patrons and Benmax is pleased to be a partner on this large multistage development project.

Working alongside Queensland Investment Corporation (QIC) and Construction Control, Benmax has delivered numerous projects at the site over recent years including several stages of enabling works, various tenancy and amenities upgrades, refurbishment and expansion of retail spaces, and upgrade works in The Piazza alfresco dining and entertainment precinct.

The largest of the projects delivered to date has been the mechanical services contract for Stage 2 Enabling Works won by the team in late 2016. This project included the demolition of three existing plant rooms, the construction of two new plant rooms and the extensive associated mechanical services work all while the centre remained open and operational.

One of the major challenges of the project was maintaining uninterrupted operation of the Centre’s cooling conditions whilst the team constructed and reconfigured multiple new central energy plants within the same occupied space as the demolished plant rooms. The work of the Benmax digital engineering team in utilising BIM and 3D viewing platforms greatly assisted the site team and broader project partners to coordinate the work programme to ensure supply was maintained to the Centre while the work was successfully completed.

Benmax completed work on this stage of the project in early 2018 and has gone on to deliver further stages of work in the major redevelopment project.

Major refurbishment works at Castle Towers retail precinct including demolition of three existing plantrooms and construction of two replacement plantrooms plus associated works.

Find out how we can help you

HVAC design specialists since 1986. Best practice is our standard.

We design, build and maintain specialised mechanical systems for commercial and industrial facilities to provide healthy, safe and efficient indoor environments for people to live, work and play. We’ve spent three decades building our reputation. We’ve done that by doing a good job, and getting another job.

This website uses cookies
We use cookies to personalise content and ads, to provide social media features and to analyse our traffic. We also share information about your use of our site with our social media, advertising and analytics partners who may combine it with other information that you’ve provided to them or that they’ve collected from your use of their services.