Verizon Data Centre
Project Overview
Sector: | Data & Communications |
Location: | Australia - Canberra |
Year Completed: | 2009 |
Project Features
- Tier III Certified Data Centre
- N+1 redundancy
- Free cooling chilled water system with 90,000 litre storage tank
Project Details
The experience and knowledge of the Benmax team in data centre installation works was crucial in delivering this project. Critical to Verizon’s operations in Canberra, the mechanical services are required to operate at the highest level of quality, reliability and due diligence.
This building was designed to achieve Tier III Data Centre Certification as defined in TIA942. A Tier III Data Centre requires that all critical systems have concurrent maintainability and testing capability. The facilities must be capable of being maintained, upgraded and tested without interruption of the data centre’s operations. This typically involves either N+1 or 2N redundancy.